Galvin Middle School; Wakefield, MA

Construction of the academic portion of the new Galvin Middle School was completed and was opened to students on 9/3/14. The new school serves grades 5-8 through a team-teaching approach. The project was accomplished in five major phases. Phases 1-3 are complete and occupied. The remaining 2 phases, which are comprised of the auditorium, gymnasium and remaining play fields, are completed. Phasing sequences were orchestrated to allow the existing school to remain in operation throughout construction until the new school was occupied. The academic portion was in operation for the 2014- 2015 school year. The auditorium was completed in October 2014. The entire Galvin Middle School was completed in the summer of 2015.

Building Area Project Cost Delivery Method Scope
187,733 SF $74.4M CM@R Owner’s Project Manager