Projects

ST. JOHN MEDICAL CENTER; WESTLAKE, OH

NV5 was retained as the Owner’s Scheduling Consultant for a six (6) phase build-out. Phase 1 included a full renovation of the outpatient entrance, lobby, gift shop, and chapel.  Phase 2 was composed of two (2) major building additions including new PED’s, Surgery Recovery, and a new Main Visitor Lobby.  Phases 3 through 6 included adding  three (3) operating rooms, renovation of surgery support areas and storage rooms, renovation of respiratory therapy, radiology including relocation of nuclear medicine, both first and second floor main corridors, labs, and SDS.

Building Area Project Cost Delivery Method Scope
146,000 SF $53M IPD Project Controls